In Dripping Springs, The Sewer Plant Decides Where The Next Neighborhood Goes

If you're buying a new home in Dripping Springs before 2029, the most useful question for the builder is who treats your wastewater. The city's main treatment plant has been close to full for months. It won't take most large new subdivisions until an expansion is built, and that expansion isn't scheduled to finish its first phase until about 2029. Until then, new neighborhoods get built where developers can handle their own wastewater. Homes in the same part of Hays County can sit on different systems, with different operators, different long-term plans and different costs to carry.

The Plant Won Its Case And Still Can't Take A Subdivision

The city applied for a Texas Pollutant Discharge Elimination System permit in 2015, and the Texas Commission on Environmental Quality granted it in 2019. Then came a lawsuit from the Save Our Springs Alliance over possible discharge into Onion Creek. Community Impact reported that the Texas Supreme Court upheld the permit on April 11, 2025. The permit allows about 822,500 gallons per day of treatment.

The plant that exists today, the South Regional Wastewater Reclamation Facility, handles about 162,500 gallons per day. Community Impact's August 2026 report said it has been "near capacity and unable to accept most new large connections" for several months. Since 2015, the number of city wastewater customers has grown by about 600%.

Deputy City Administrator Shawn Cox told Community Impact the city can still accept some new connections. "It hasn't stopped developments from being able to tie in," Cox said. "It's just we're not going to tie in a large subdivision to it because it can't handle that." In the same article, Utilities Director Gray Lahrman said the city won't add most new large residential connections except in special circumstances, such as an existing agreement.

So the court ruling settled whether the plant can grow. It didn't add any capacity. The capacity depends on the construction schedule.

The Calendar Behind Every New Plat

Here is the timeline the city has published, based on Community Impact's August 28, 2026 report:

  1. February 2026: City council selected three firms for the South Regional expansion.
  2. May 2026: Council approved higher wastewater rates.
  3. July 2026: The Texas Water Development Board approved additional wastewater funding.
  4. December 2026: The city plans to issue a notice to proceed for phase one to the winning bidder.
  5. 2027: Phase-one construction is scheduled to start.
  6. 2029: Lahrman estimated phase one would take two and a half to three years. The city plans to design phase two while phase one is being built.

That schedule has already slipped. An earlier city wastewater update planned to bid the plant and the west interceptor in the last quarter of 2025, and estimated about two years of construction once contracts were awarded. The funding figure isn't settled either. The same Community Impact article says the city secured an additional $51.5 million through a TWDB loan, while its timeline says the board approved a $53 million application in July.

This calendar matters to buyers because every subdivision that can't wait for it has to find another way to handle wastewater.

Where The Growth Went Instead

The city had a temporary development moratorium in 2021 and 2022 because there wasn't enough wastewater capacity. When it was lifted, officials warned that projects would still face problems. Developers have since built their own temporary treatment plants. Another option is pump-and-haul, where wastewater is stored in a tank that is emptied on a schedule and trucked elsewhere for treatment. According to Community Impact, the city has approved only three pump-and-haul plans in recent years. Projects using these alternative systems will add more than 3,800 lots or units to the Dripping Springs area.

City project records name some of them. Every facility entry below was listed as waiting on resubmittal, so these are proposed plants. The records don't show that they are operating or serving occupied homes.

Project Location in city records Wastewater approach listed Status in city records
Wild Ridge Goose Island Drive Phase one of a temporary wastewater treatment plant Waiting on resubmittal
Village Grove South Rob Shelton Boulevard Village Grove Wastewater Treatment Plant Waiting on resubmittal
Double L Ranch Northwest of RR 12 and Event Center Drive Reclaimed water production facility and pump-and-haul Waiting on resubmittal
Lunaroya Phase 2 Silver Creek Road 28 single-family lots with on-site sewage Listed in city records
New Growth U.S. 290 and Roger Hanks Parkway Waiting on city plant capacity Waiting on resubmittal

New Growth shows what happens to a project that has nothing to fall back on. The city project list calls it a mixed-use project with 240 residential units. The 2026 State of the City report lists it at 245 lots. Either way, Community Impact's August report says the project is waiting until the South Regional plant has more capacity, while subdivisions with their own wastewater arrangements keep adding lots.

Why A Private Plant Sits Where It Sits

Madelynn Estates, near Woods Loop and RR 150, shows how this works on the ground. Community Impact reported in October 2025 that Allied Development proposed a wastewater plant for the project. Final TCEQ approval was still pending after an October 6 public meeting. The proposed plant would sit 1,500 feet from Onion Creek and 2,500 feet from the city plant, and TCEQ staff said there was no collection pipe it could connect to the city plant through. An earlier version of the plan called for 113 homes on 52 acres, and the developer described 45,000 gallons per day as the worst-case discharge in the permit application. That status is from October 2025 and may have changed.

Being half a mile from the city plant doesn't help without a pipe to it. That's why these private applications keep appearing. TCEQ's pending land application permit list shows other Hays County applications too, including one from Aqua Texas for a Wood Creek plant that was declared administratively complete in January 2026.

The city has also said temporary systems aren't meant to be permanent. Its wastewater update lists a goal to "determine best options for serving current subdivisions through wastewater agreements including transitioning away from temporary solutions." If a home is in a subdivision on a temporary plant, the terms of any future switch would be set in agreements between the developer and the city. Those documents are worth asking for during a purchase.

These are useful questions to ask a builder or developer:

  • Is the home served by city sewer, a developer or district plant, pump-and-haul, or an individual on-site system?
  • Who owns and operates that system today?
  • Is there a written agreement for eventually connecting to city service, and what does it say about timing and cost?
  • Which special taxing districts apply to this parcel?

City Customers Already Pay More

Connecting to the city doesn't mean wastewater stays cheap. In May 2026, council raised wastewater rates for the first time since 2022. The residential base fee went from $28.88 to $43.32, and the usage charge went from $4.05 to $5.67 per 1,000 gallons. The new rates started showing up on September 2026 bills. For an average residential customer using 6,578 gallons a month, Community Impact calculated the bill rising from $55.52 to $80.62, an increase of more than 45%. Community Impact's May report used a 5,262-gallon example, which goes from $50.19 to $73.16.

The city is also covering part of the cost from its general fund. Its contribution rises from $980,000 to $2.5 million through 2030 to offset wastewater costs and limit increases in customer fees. Lahrman told Community Impact the main reason costs went up was "the significant growth in the city's wastewater customer base."

The Tax Stack Sits On Top Of The Utility Bill

The utility bill is a monthly charge. Infrastructure in master-planned communities is often paid for through special districts that appear on the property tax bill. The Hays County tax estimator lists possible taxing units including Headwaters MUD, Springhollow MUD, Dripping Springs MUD 1, Wild Ridge MUD, Hays County MUDs 7A and 7B, the Heritage PID and the Driftwood Economic Development MMD. That means the exact address determines which ones apply. The estimator shows tax-year 2025 calculations.

Here are two current examples:

  • Headwaters MUD: Its published 2026 tax table shows a total rate of $0.90 per $100 of value, the same rate every year since 2020. For 2026, all $0.90 goes to debt service and none to maintenance and operations.
  • Heritage PID: The city's 2026 annual service plan update sets area-wide installments due January 31, 2027. They are $556,354.19 for Improvement Area 1, $533,175.43 for Area 2, $344,894.12 for Area 3A and $223,956.99 for Area 3B. Those totals are divided among the assessed parcels. A single home's share appears on the assessment roll. According to the city's September 1, 2026 staff report, the update didn't change the underlying installment amounts or create a new assessment.

The city's own property tax rate went down. Community Impact reported on October 8, 2026 that the city adopted a FY 2026-27 rate of $0.219217 per $100 after correcting a calculation error. The September hearing agenda had listed $0.2729. That number covers the city only and doesn't include any MUD or PID. Two homes inside the same city limits can have the same city rate and very different total tax bills.

Quick Answers

Will the Onion Creek discharge permit be used routinely? Lahrman told Community Impact the city doesn't plan to discharge into Onion Creek except in emergencies. Treated water that can't be used for irrigation will be stored.

Can a new home still get city sewer today? Some new connections are still being accepted. Most large subdivisions aren't, unless there are special circumstances such as an existing agreement.

When does capacity actually increase? The city's published schedule has phase-one construction starting in 2027 and finishing around 2029. An earlier target of bidding in late 2025 has already been pushed back.

Do the Wild Ridge, Village Grove or Double L Ranch plants serve homes now? In the city records reviewed, each one was listed as waiting on resubmittal. That shows a plant was proposed. It doesn't show that it's running.

If you're looking at new construction in Dripping Springs, wastewater service and the district tax stack belong in your comparison alongside the floor plan and the lot. Steve Dedear can help you get the service agreements, district details and assessment figures for any home you're considering before you sign. Explore My Properties.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.